| PROJECT PHASE |
ACTIVITY |
PURPOSE |
| planning |
planning meeting |
to agree timetable & arrange next week |
| |
day centres Xmas parties ~ no activities |
|
| research |
visit to Willow Tree Farm & Carter Lane garden, Shirebrook |
to gather ideas for Mastin Moor |
| |
BANK HOLIDAY ~ no activities |
|
| |
BANK HOLIDAY ~ no activities |
|
| research |
visit to Tapton Lock Sensory Garden & Mill Garden Centre |
|
| planning |
planning meeting; then look at what we have learnt so far * |
|
| research |
visit to Carsington Water |
|
| research |
visit to Clay Cross Hall sensory garden |
to produce a shortlist of our favourite ideas |
| design |
look at all the ideas & choose elements to be included |
so that the plans can be drawn up |
| design |
draw up a plan and submit it to the committee |
to gain agreement for the final design |
| purchasing |
commission/order structures; order hard landscaping |
to ensure that all will be available on time |
| purchasing |
order/purchase seeds/plants |
and any adjustments needed to the plans |
| purchasing |
order/purchase plants & materials |
are agreed with the MMAA Committee |
| building |
mark out the garden |
so that the plans can be implemented |
| building |
create beds et cetera |
to create the sensory garden |
| building |
|
|
| building |
|
|
| |
BANK HOLIDAY ~ no activities |
|
| building |
install features |
|
| planting |
plant beds as per design |
|
| planting |
|
|
| |
BANK HOLIDAY ~ no activities |
|
| planting |
|
|
| planting |
|
|
| |
BANK HOLIDAY ~ no activities |
|
| planting |
|
|
| planting |
add finishing touches |
|
| planting |
|
|
| OFFICIAL OPENING DURING LOVE PARK WEEK EVENT |
to publicise our work and achievements |
| |
celebration |
to thank everyone for their hard work |
|